Tasks are only showing up on a week and month view and not day view in the Calendar. Is this by design?
Hi Violet,
No this is not by design, it looks like a bug that snuck it's way in. I have filed this for you and we will address it shortly -- thanks for pointing this out. The Bug # we are tracking for this internally is 5550.
Matt
This does not seem to be addressed yet. Any timeline on it?
Hi Earl, I saw this in your environment but wasn't able to reproduce it on Rollbase.com or a local environment here. Is this something you can reproduce easily using a Rollbase.com account? That would make it easier for us to figure out what is happening
Thanks,
Matt
Matt,
I tested this in the Rollbase.com account, and there are no issues seeing the tasks in a "day" view.
This only seems to occur in our mission.do instance. What do we need to do to correct?
That is the question, I am not sure why it isn't working in your environment. I expected to see JavaScript errors in your environment that would lead me to the problem but I did not see any.
I will take another look, we need to do some creating debugging here to somehow find out why this is only happening in mission.do
Hi Matt,
parent.date is not a valid date
All of the events in the rbv_events array have invalid dates.
It would be easier to debug if the JS file was not compressed and had each statement on it's own line - you could step through each javascript line using chrome dev tools or similar add-on. Anyways, this might give you a starting point of where to look.
These all seem like perfectly normal dates.
FYI we are still looking into this issue.
What is the status of this issue? I have the same problem.
Can you reproduce this? If so please send us steps if possible.