I am very new to Progress and need some guidance.
My client has 2 versions of Progress that currently connect to Oracle7 (7.3.4)
and want to upgrade to Oracle 8i (8.1.7) or Oracle9i (9.2.0). The database
would be running on Sun Solaris Unix server.
The versions of Progress are:
Progress 8.3 B character based runing on Solaris 2.6
Progress 7.3 E GUI running on Win2000 clients.
Upgrading Progress would result in major rewriting which is not an option at
this time.
Is there a way of getting these applications to connect to one of these newer
databases with a minimal amount of change to the app.
Thanks.
John
/*
John,
I can only give very general advice but I can say that I recently upgraded
my Oracle Dataserver app from 8i to 9i with no rewrites or tweaks at all. Progress
client v9.1c/9.1d.
HTH
Nick